Use of support vector regression to improve computational efficiency of stochastic time-cost trade-off

研究成果: 期刊貢獻文章同行評審

20 引文 斯高帕斯(Scopus)

摘要

Stochastic time-cost trade-off has been a popular object of investigation in past decades because there are uncertain factors that can be considered when determining the appropriate trade-off between project completion time and cost. Previous studies, however, have implemented a double loop procedure, which performs optimization in the outer loop and simulation in the inner loop. The double loop procedure is ponderous because it requires an unacceptably long computation time (taking hours or days), even for a small to medium project. The present study proposes an integrated system that converts the double loop to single loops,thereby dramatically reducing computation time. This is done by incorporating a support vector regression model to obtain a decision function, which will be used to replace the time-consuming Monte Carlo simulation to evaluate the objective function values for individual solutions. With the objective function values, a multiobjective particle swarm optimization algorithm is developed to search for the Pareto front composed of nondominated solutions. It has been empirically shown that the proposed system significantly outperforms the conventional double loop procedure because the former can consistently generate a better Pareto front (with a larger hyperarea ratio) hundreds of times faster by using much less computation time. The Student's t test is performed to validate the superiority of the proposed system. The contribution of the proposed system is multifold. First, improved computational efficiency is essential for the widespread acceptance of the stochastic time-cost trade-off analysis in practical applications. Second, with less computation time spent in simulation, efforts can be focused on the search for much better nondominated solutions. Third, the proposed system can incorporate the risk attitudes of the decision makers into the analysis by allowing them to specify the probability that they can tolerate for project duration (cost) to exceed a certain limit.

原文English
文章編號04013036
期刊Journal of Construction Engineering and Management
140
發行號1
DOIs
出版狀態Published - 1月 2014

指紋

深入研究「Use of support vector regression to improve computational efficiency of stochastic time-cost trade-off」主題。共同形成了獨特的指紋。

引用此